We will be closed for Labor Day on Monday, September 7th

Close

Electric Rates

Avoided Costs (for Net Metered Services)

Availability

Available to all customers with a qualifying contractual generating resource up to and including 25 kW or a net metered service resulting in a net metered flow of 25 kW maximum into BLEC’s system, at any time.

Type of Service

Available to all services BLEC offers.

Monthly Rate

Customer shall pay the Electric System Charge as classified in their rate schedule, and any other charges as specified in the appropriate rate class they are classified in.

Terms of Payment

The above rates are net. Penalties will be assessed in accordance with established rules and regulation.

Avoided Costs

For the purpose of calculating the avoided cost in crediting a net metering customer, the Cooperative shall use the projected avoided wholesale cost of power. The avoided cost will be paid to the customer for any energy flowing into BLEC’s system net of all other flows for the month.

YearJanFebMarAprilMayJuneJulyAugSeptOctNovDec
202643.1837.90
30.36
23.5422.6027.1940.4047.1548.1641.3444.1149.83
Area Lights
  • 100 watts High Pressure Sodium or Equivalent $15.85
  • 200 watts High Pressure Sodium or Equivalent $28.98
  • 400 watts High Pressure Sodium or Equivalent $47.07
Rate Schedule Green Power (GP)

Type of Service

On a voluntary basis, consumers may support the continuing operations of such plants as the Coffin Butte Landfill Methane Resource Project and promote the expansion of this type of alternative energy source. At the consumer’s request, the Cooperative will direct an additional dollar amount on their electric bill to help fund the production of Green Power from the Coffin Butte Landfill Methane Resource Project.

Monthly Support Charges (Over and Above the Applicable Rate)

  • 100 kWh blocks at $2.00 per block
  • 1000 kWh blocks at $15.00 per block
Rate Schedule C1: Commercial without kW Charge

Monthly Rate

Distribution Capacity Charge (per meter):

  • C-1 Single Phase $44.01
  • C-1 Poly Phase $49.60

Distribution Services Charge

  • C-1 Single and Poly Phase $20.15
    (Only applies to the first meter on an account at the same service location)

kWh Usage Charge

  • 1-2000 kWh per month $ 0.0629
  • Over 2000 kWh per month $ 0.0818
Rate Schedule R/GS: Residential and General Services

Monthly Rate

Distribution Capacity Charge (per meter):

  • Single-phase $40.47
  • Three-phase $46.02

Distribution Services Charge:

  • Single and Poly Phase $18.53
    (Only applies to the first meter on an account at the same service location)

kWh Usage Charge:

  • 0-2000 kWh per month at $ 0.1119
  • Over 2000 kWh per month $ 0.1288